|












| |
Hans J Marter
16 April, 2008
WORK
ON dredging Lerwick’s north harbour to a depth of nine metres is set to start
next week, creating up to 30 local jobs over the next eight months.
The £12 million project will be carried out by Westminster Dredging Company, one
of the world's largest dredging contractors.
It will be the biggest project ever undertaken at the port, allowing large ships
to enter the industrialised north of the harbour.
The job was delayed by almost three years after a bitter conflict between
Shetland Islands Council and Lerwick Port Authority over a proposal to build a
bridge to the nearby island of Bressay.
Legal action by the council in 2005 forced the port to pull out of a £7 million
contract with Belgium dredging company Jan de Nul.
The dredging contract was re-advertised immediately after the Court of Session
threw out the council’s interdict in January 2006, but the port is still
awaiting payment of a £5.25 million compensation claim from the SIC.
The port has wanted to develop a deep water access since the beginning of the
decade, alongside plans to reclaim land for industries such as oil rig
decommissioning.
Almost 490,000 cubic metres of good quality material will be removed from the
seabed during the eight month project, taking it from a depth of six to nine
metres.
Most will be used to reclaim 5.8 hectares (14.4 acres) of land to the north of
Greenhead Base, creating an additional area for decommissioning offshore oil and
gas production facilities. The rest of the material will be stockpiled there for
later use.
Port chief executive Sandra Laurenson said: "The deeper and wider access and the
deepened berths will suit the larger vessels now operating and will be of
particular benefit to the pelagic fish sector and offshore industry
decommissioning, while the reclaimed land will offer opportunities to
decommissioning and other industries."
Starting next week the large, self-contained, trailer suction dredger
Waterway will spend around a month removing the softer seabed material by
sucking it into an onboard hopper.
It will then move to the reclamation site where the material will either be
pumped ashore through a temporary pre-laid pipeline, or blown ashore if
conditions are right.
The back-hoe dredger Manu Pekka will then use its large excavator plant
to dig out weathered rock, as well as fresh rock pre-blasted by a ‘drill and
blast’ barge.
The back-hoe will load the material into two self-propelled hopper barges for
delivery to the reclamation site where it will be dumped or, to assist
placement, some may be trucked to the site. The Manu Pekka will operate
from mid May to September.
In an overlapping phase, the ‘drill and blast’ barge will be operating from
mid-June to August.
Meanwhile Westminster Dredging has established project offices at SBS's
Greenhead Base. The company is bringing up a workforce of between 40 and 50
people, and in addition as many as 30 jobs could be created locally for the
duration of the project.
Local civil engineering specialists Arch Henderson LLP is responsible for the
design and supervision of what will be one of the largest marine civil
engineering projects to be completed in Scotland this year.
|