|
12 September, 2008
LERWICK Port Authority is preparing plans to build deep water quays in the north
harbour as the £12 million dredging project reaches completion.
Contractor
Westminster Dredging are set to complete the deepening of the harbour’s north
entrance on schedule, with some dredging plant set to leave the islands in the
next few days.
The navigational channel in the harbour’s north entrance has been widened and
deepened to nine metres to accommodate the larger ships which now want to use
the port.
The Greenhead Basin and landing berth at Shetland Catch fish factory are now the
same depth, allowing the larger fishing boats and the vessels involved in the
oil decommissioning industry to use the harbour more easily.
Extra dredging has deepened the landing berth access at the Heogan fishmeal
factory to eight metres, Mair’s yard is now six metres deep and an area in the
inner harbour anchorage has been lowered to 10 metres.
Contractor Westminster Dredging is preparing surveys of the dredged areas prior
to replacing the navigation buoys to mark the newly deepened channels.
Now drill and blast operations have been completed ahead of schedule by the
barge Playmate, which has been released along with one of the disposal barges.
The backhoe dredger Manu Pekka is now finishing off and should be released next
week with the second disposal barge.
Harbourmaster Captain Calum Grains said “The dredging phase of the project is on
schedule. We expect to see a number of large ships transiting through the
harbour to and from Greenhead Base this winter.”
The final job involves protecting the land reclamation site created north of
Greenhead Base. Large rock armour stone has been delivered from Norway and
materials are now on site to complete the works by early November. A total of
14.4 acres of land has been created by re-using the dredged material.
Lerwick Port Authority chief executive Sandra Laurenson said: “The authority has
already started planning its next capital projects to provide deep water quays
enabled by the dredging.
“The 2008 dredging works are part of the constant evolution of the harbour to
keep pace with shipping. We forecast that dredging will be required again in the
harbour in the future.”
|